Calm blue-green lagoon water beside a sandy shore and native coastal grasses in soft autumn sunlight.

Colorado Lagoon's Water Reached the Bay Before Its Trails Did

Until this summer, water moving between Colorado Lagoon and Marine Stadium went through a buried box culvert. Now it flows through an open channel cut through Marina Vista Park. The City's riprap lines the channel slopes, a new decomposed granite trail runs beside it, and there are bridges with safety picket fencing at each end.

The water arrived first. According to the City of Long Beach project page, crews pulled the first sheet piles at Eliot Street by the week ending Aug. 21, 2026. That opened the channel and restored natural tidal exchange between the lagoon and Marine Stadium and Alamitos Bay. The land side is following on its own slower schedule, one street, trail and planting bed at a time. For anyone who uses this corner of East Long Beach, the useful question this month is which parts run on a fixed schedule.

Four years of detours, then the water came back all at once

The lagoon closed to vehicle and pedestrian traffic in November 2022 so crews could reconnect it to Marine Stadium. Longbeachize reported in October that the project was "years past its initial completion date." It also noted that the surrounding streets were last promised to reopen at the end of 2024, before asbestos was found and caused more delays.

The water work then finished quickly over late summer. The City's project page lays out the order:

  • July 2026: a hydraulic shutdown between Alamitos Bay and the lagoon, with aerators running and consultants monitoring water quality
  • August: the old box culvert and its wing walls were demolished, and the slopes were graded and protected with riprap
  • Week ending Aug. 21: the first sheet piles came out at Eliot Street and the open channel was activated
  • Aug. 31: sheet pile removal began near the Colorado Street bridge during normal working hours, after the contractor worked out other safety measures with SCE and the crane operator
  • Early September: every sheet pile segment except one damaged piece had been removed, and the crane left the site

Cranes for that work were staged at Larry Curtis Park and Alamitos Heights Park. The sheet piles they removed had been installed in 2023 so crews could build the bridges in dry conditions. The City describes the activated channel as a major milestone toward the vision in the 2005 Master Restoration Plan, a goal set more than 20 years ago.

Colorado Street came back first

The first part of daily routine to return was a road. Colorado Street, on the north edge of the project, reopened to vehicles on Wednesday, Sept. 30, according to the City's project bulletin for the week ending Oct. 3.

That reopening restored a commuter shortcut. Longbeachize described the route as a way to reach Pacific Coast Highway or Studebaker through Loynes Drive without using 7th Street, and noted that it opened to cars and bikes again. It also had an operational purpose. The City's September update says the Colorado Street reopening restores access for Fire Station 14. The October bulletin adds that Public Works planned to move the station's traffic to Colorado Street before starting the Eliot Street and bike path repairs.

The order makes sense. Eliot Street can only reopen after Colorado Street takes over its traffic and the remaining repairs on the south side are finished.

The pieces still on the City's punch list

Most of what remains is landscaping and access, and the City has tied each piece to a condition instead of a fixed date. The table below shows how the City laid out each piece in its bulletin for the week ending Oct. 3.

Piece of the project The City's plan as of its Oct. 3 bulletin
Eliot Street, south edge along Marine Stadium Reopens after repairs to the concrete bike path at 3rd Street and Paoli, damaged by temporary emergency vehicle routing, and after field offices, trailers and equipment are removed
Trail between the channel and Marina Vista Park, plus lookout points Decomposed granite installed, with certain trail and overlook areas scheduled to open in October once punch-list items were done
Sod, native plants, trees and hydroseeding Targeted for October and November, after the soil in the channel area meets the required conditions
Interpretive signs on lagoon biodiversity and ecology Scheduled for installation along the trail in September and October
Manhole adjustments required by the County Sanitation District Concrete collars around lids, with steel plates and temporary traffic controls where work remains

The planting window comes from the soil. The City says soil nourishment and amendment in the channel area began in late September, that soil leaching still had to happen, and that upland planting would follow once the required soil conditions were reached. Even after planting begins, the City's September update says orange protective fencing stays up so plants have time to mature. Some fencing around the new green space is part of the landscaping plan, not a sign that construction has stalled.

The Friends of Colorado Lagoon point readers to two places for status changes. One is the 3rd Council District's weekly newsletter, Voice of the Third. The other is the City project page, which offers automatic email updates.

The routine that runs on a fixed schedule

The pieces above depend on soil, repairs and inspections, so their timing can shift. The parts of the lagoon below run on schedules that don't depend on construction, and they show how the area works on a normal week.

The Wednesday farmers market. Throughout construction, the City's project page has listed the farmers market as open Wednesdays from 3 to 7 p.m.

The swimming beach. The City's Colorado Lagoon aquatics page lists a sandy swimming beach, restrooms, turf picnic areas and parking on both the north and south shores. Water status changes from sample to sample. On the City Health Department's recreational water page, the Nov. 9 update listed both Colorado Lagoon-West and Colorado Lagoon-East as open. The department advises staying out of the water for 72 hours after significant rain and following posted beach warnings. November is when rainy days start to matter for that advice, so check the page before a swim.

Marina Vista Park. The park has been open since July 31. Construction fencing remains around active work areas. It is also where the new channel connects to the wider bike network. According to the City park directory, a bike path crosses the park and joins the path along Boat House Lane toward the rowing center and the Jack Dunster Marine Preserve. The park also has soccer and softball fields, tennis courts, play equipment and picnic areas.

Second Saturdays with Friends of Colorado Lagoon. The nonprofit hosts a session at WAMSEC on the second Saturday of each month from 10 a.m. to noon. It opens with a short history of the lagoon and a talk on its ecology, and usually includes hands-on work such as planting, weeding or trash removal. November's session was on the 14th, so the next one is Saturday, Dec. 12. The group asks participants to wear closed-toe shoes that can get dirty and to bring water, plus sunscreen, snacks and work gloves as needed. The December session is the first scheduled one since the planting window the City set for October and November.

Following the new water down to Marine Stadium

The channel was built to tie the lagoon to Marine Stadium and Alamitos Bay, so a walk or ride along it ends at the stadium. The next event there is close. Visit Long Beach lists the Patchwork Show: Modern Makers Festival at Marine Stadium, 490 Bay Shore Ave., on Saturday, Nov. 28. Starting at Marina Vista Park and following the Boat House Lane path toward the rowing center puts the new channel at the beginning of that trip.

The lagoon also borders a larger recreation area to the north and west. The City lists Recreation Park as a 229-acre center with an 18-hole course and a 9-hole course, Recreation Park North 18 and South 9, along with other sports and recreation facilities. With Colorado Street open again, the lagoon's north edge has a direct route back to it.

Longbeachize summed up the project's main point as returning the lagoon to its former glory by reconnecting it more fully to Marine Stadium through a new tidal channel. Tidal water has been moving through that connection since late August. Eliot Street, the lookout points and the native planting will each open after its own condition is met, and the City project page posts each change as it happens.

If changes like this are part of how you're thinking about a move to East Long Beach, or somewhere between the coast and the desert, Darcy Barajas and The Barajas Team can show you how the area's streets, parks and weekly routines fit together before you choose where to live. Schedule a Relocation Consultation, and we'll start with how you plan to spend your weekdays and weekends.